Client Charter

Achievement

Fulfilled Client Charter Duration / Standard

Exceeded Client Charter

Number Fulfilling
Standard

%
Fulfilling
Standard

Number
Exceeding
Standard

%
Exceeding
Standard

1.95% physical projects implemented according to schedule (P.01)
206 100% - -

There are 206 active projects until 30 April 2018.

On schedule  = 192 projects (93.2%)
Belum mula   = 1 (0.5%)
Completed    = 13 projects (6.3%)
Late/pending   = none (0%)

2. Plan, coordinate, monitor and evaluate the Socio-Economic Survey within the stipulated duration.
2 100% - -
Addition of one (1) new project. Publication of the Penang State Transport Master Plan Blueprint.
3. All official government functions are carried out in a professional, precise and effective manner.
 -  - -
 -
-
4. Student loan applications are processed and the results are disseminated within one (1) month from the closing date of application.
Closing date for Student loan Applications 2018 is on 30 August 208. There is no achievement report this month.
5. Application (of which forms are complete) and registration of Affordable Housing (RMM) 'A', 'B', 'C1', 'C2' & 'C3', State Government Public Housing are processed whitin one (1) day after they are received.
1713
 100% - -
6. Feedback of complaints are disseminated within fifteen (15) days from the date they are received.
195 complaints
100% - -
7. Payment is made within seven (7) days upon receipt of complete application documents.

4180

 100% - -

8. Executive Council (EXCO) Meeting papres are prepared within seven (7) working days from the date directive is received.

413

100%

-

-

9. Exco decisions are mplemented not later than saven (7) days after the Exco minutes is confirmed.

413

100%

-

-

10. State Assembly matters are implemented efficiently according to schedule and dates stipulated.

-

- - -
State Legislative Assembly date is set to be in May dan November 2018.
11. Replies to applications/matters on human resource services, which are complete, are processed and results given within seven (7) days from the date they are received.

3321

100%

-

-

Portal Rasmi Kerajaan Negeri Pulau Pinang

Paras 25, KOMTAR, 10503 Pulau Pinang
Tel : +604-2621957 
Complaints Line : +604-2642020
Fax : +604-2634940
Email : webmaster[at]penang[dot]gov[dot]my  

Paras 25, KOMTAR, 10503 Pulau Pinang
Tel : +604-2621957 
Complaints Line : +604-2642020
Fax : +604-2634940
Email : webmaster[at]penang[dot]gov[dot]my  

1757918
Capaian Bulan Ini:: 2,805
Capaian Keseluruhan: 1,757,918
  • Dikemaskini pada: 03 February 2026.

Copyright © 2022 Kerajaan Negeri Pulau Pinang